Question: Please help I am lost and missed this on homework. Thanks. MGMT 5325 6. A partially solved PERT problem is detailed in the table below.

Please help I am lost and missed this on homework. Thanks. MGMT 5325

6. A partially solved PERT problem is detailed in the table below. Times are given in weeks. (10 points)

Activity

Preceding

Optimistic

Time

Probable

Time

Pessimistic

Time

Expected

Time

ES

EF

LS

LF

Slack

Variance

A

--

7

7

13

B

A

4

4

10

C

A

1

2

6

D

A

3

7

8

E

D

1

5

6

F

C

5

6

13

G

H, E

4

7

7

H

B

1

4

7

I

B, C

5

6

13

J

F, I

4

5

12

K

G, J

2

3

7

a. Calculate the expected time and variance for each activity. Enter these values in the appropriate column in the table above.

b. Which path(s) form the critical path?

c. What is the estimated time of the critical path?

d. What are the project variance and the project standard deviation?

e. What is the probability of completion of the project within 31 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!