Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected

A partially solved PERT problem is detailed in the table below. Times are given in weeks.

Activity

Preceding

Optimistic

Time

Probable

Time

Pessimistic

Time

Expected

Time

Variance

A

--

7

9

14

B

A

2

2

8

C

A

8

12

16

D

--

3

5

10

E

C

4

6

8

F

B

6

8

10

G

F

2

3

4

H

D, E

2

2

8

I

G

6

8

16

J

H

4

6

14

K

I, J

2

2

5

a)Calculate the expected time for each activity.

b)Which activities form the critical path?

c)What is the project variance?

d)What is the project standard deviation?

e)What is the probability of completion of the projectAFTERweek 40?

explain please

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!