Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected
A partially solved PERT problem is detailed in the table below. Times are given in weeks.
Activity
Preceding
Optimistic
Time
Probable
Time
Pessimistic
Time
Expected
Time
Variance
A
--
7
9
14
B
A
2
2
8
C
A
8
12
16
D
--
3
5
10
E
C
4
6
8
F
B
6
8
10
G
F
2
3
4
H
D, E
2
2
8
I
G
6
8
16
J
H
4
6
14
K
I, J
2
2
5
a)Calculate the expected time for each activity.
b)Which activities form the critical path?
c)What is the project variance?
d)What is the project standard deviation?
e)What is the probability of completion of the projectAFTERweek 40?
explain please
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
