Question: Please Help, i have 2 hours to submit INSPECT gave the atelier only 245 days to make the changes; if the changes were not made

Please Help, i have 2 hours to submit

INSPECT gave the atelier only 245 days to make the changes; if the changes were not made by then, the atelier would be fined $300,000. The atelier determined the activities in a CPM/PERT network that would have to be completed and then estimated the indicated activity times, as shown in the following table.

  1. What is the probability that the atelier will be fined $300,000?

Activity

Activity Description

Activity

Predecessor

Time Estimates (weeks)

o- m- p

a

Order new machinery

-

1-2-3

b

Plan new physical layout

-

2-5-8

c

Determine safety changes in existing machinery

-

1-3-5

d

Receive equipment

A

4-10-25

e

Hire new employees

A

3-7-12

f

Make plant alterations

B

10-15-25

g

Make changes in existing machinery

C

5-9-14

h

Train new employees

d,e

2-3-7

i

Install new machinery

d,e,f

1-4-6

j

Relocate old machinery

d,e,f,g

2-5-10

k

Conduct employee safety orientation

h,i,j

2-2-2

FINISH

K

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!