Question: Please help. I'm so stuck 2.Which input to the Project Communication Management knowledge area incudes information about project, Product, and process improvements? Change log Issue
Please help. I'm so stuck
2.Which input to the Project Communication Management knowledge area incudes information about project, Product, and process improvements?
Change log
Issue log
Quality
Risk report
3. A project manager is running an adaptive style project. Which process is performed once for each iteration?
Validate Scope
Conflict Requirements
Control Scope
Create WBS