Question: Please help me answer A -C Thank you! 2) Preceding Optimistic Activity A B 5 Probable 11 3 Pessimistic 14 9 3 6 10 14

Please help me answer A -C Thank you! 2)

Please help me answer A -C

Thank you!

2) Preceding Optimistic Activity A B 5 Probable 11 3 Pessimistic 14 9 3 6 10 14 D 3 5 7 11 E 4 6 F AB B DE F 6 8 13 G 6 2 3 4 3 H 9 a. b. Calculate the expected duration and variance of each activity. Calculate the expected duration and variance of the critical path. Calculate the probability that the project will be completed in less than 28 weeks. c

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!