Question: PLEASE HELP ME ASAP!!! Given the following project network, baseline, and status information, develop status reports for periods 5 and 10 and complete the performance

PLEASE HELP ME ASAP!!!

Given the following project network, baseline, and status information, develop status reports for periods 5 and 10 and complete the performance indices table. Calculate the EACf and the VACf. Based on your data, what is your assessment of the current status of the project? At completion? Answer the following questions

.PLEASE HELP ME ASAP!!! Given the following

End of period 5

task actual completed % EV $ AC$ PV$ CV$ SV$
A finished 500
B 40% 1100
C 80% 1500
D 0% 0
E 0% 0
F 0% 0
total

End of period 10

TASK

actual completed % EV$ AC$ PV$ CV$ SV$
A finished 500
B finished 2300
C finished 1700
D 35% 600
E 100% 800
F 0% 0
TOTAL

Indices summary (X.XX)

PERIOD EV AC PV CPI SPI PCIB
5
10

EACf
VACf

Question 1:

In terms of future, if the project continues to earn $________ for each dollar spent, the forecasted cost at completion would be $________. A.)

A.)1.02 | 7254.90

B.)1.00 | 7400.00

C.)0.98 | 7573.47

D.)0.96 | 7608.33

Question 2: the project would then be forecasted to come in ________ budget.

A.) right on

B.)$145.10 under

C.)$208.33 over

D.) $173.47 over

Question 3: At the end of Period 10, the project is not performing well in terms of ________.

A.)both cost and schedule

B.)At the end of Period 10, the project is actually performing well in terms of both cost and schedule.

C.)cost only

D.)schedule only

Project baseline (PV) (in $) Task DUR ES LF SL 9 10 11 12 13 14 15 2 Budget (PV) 0 1 2 3 4 5 6 7 8 400 200 200 2400 200 600 200 600 200 600 1500 200 400 500 100 300 1600 400 400 400 400 12 2 900 | 300 | 400 200 1312 150 600 200 100 300 Period PV total 200 200 400 1000 700 700 500 900 800 600 400 400 200 100 300 Cumulative PV total 200 400 800 1800 2500 3200 3700 4600 5400 6000 6400 68007000 7100 7400||

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!