Question: PLEASE HELP ME ASAP!!! Given the following project network, baseline, and status information, develop status reports for periods 5 and 10 and complete the performance
PLEASE HELP ME ASAP!!!
Given the following project network, baseline, and status information, develop status reports for periods 5 and 10 and complete the performance indices table. Calculate the EACf and the VACf. Based on your data, what is your assessment of the current status of the project? At completion? Answer the following questions
.
End of period 5
| task | actual completed % | EV $ | AC$ | PV$ | CV$ | SV$ |
| A | finished | 500 | ||||
| B | 40% | 1100 | ||||
| C | 80% | 1500 | ||||
| D | 0% | 0 | ||||
| E | 0% | 0 | ||||
| F | 0% | 0 | ||||
| total |
End of period 10
| TASK | actual completed % | EV$ | AC$ | PV$ | CV$ | SV$ | |
| A | finished | 500 | |||||
| B | finished | 2300 | |||||
| C | finished | 1700 | |||||
| D | 35% | 600 | |||||
| E | 100% | 800 | |||||
| F | 0% | 0 | |||||
| TOTAL |
Indices summary (X.XX)
| PERIOD | EV | AC | PV | CPI | SPI | PCIB |
| 5 | ||||||
| 10 |
| EACf | |
| VACf |
Question 1:
In terms of future, if the project continues to earn $________ for each dollar spent, the forecasted cost at completion would be $________. A.)
A.)1.02 | 7254.90
B.)1.00 | 7400.00
C.)0.98 | 7573.47
D.)0.96 | 7608.33
Question 2: the project would then be forecasted to come in ________ budget.
A.) right on
B.)$145.10 under
C.)$208.33 over
D.) $173.47 over
Question 3: At the end of Period 10, the project is not performing well in terms of ________.
A.)both cost and schedule
B.)At the end of Period 10, the project is actually performing well in terms of both cost and schedule.
C.)cost only
D.)schedule only
Project baseline (PV) (in $) Task DUR ES LF SL 9 10 11 12 13 14 15 2 Budget (PV) 0 1 2 3 4 5 6 7 8 400 200 200 2400 200 600 200 600 200 600 1500 200 400 500 100 300 1600 400 400 400 400 12 2 900 | 300 | 400 200 1312 150 600 200 100 300 Period PV total 200 200 400 1000 700 700 500 900 800 600 400 400 200 100 300 Cumulative PV total 200 400 800 1800 2500 3200 3700 4600 5400 6000 6400 68007000 7100 7400||