Question: Please help me find the critical path (I think it is B, C, D, E, F, I, and J but am not 100%) and calculate

Please help me find the critical path (I think it is B, C, D, E, F, I, and J but am not 100%) and calculate time to completion. Please annotate these two items andplease draw out how the diagram for the critical path is supposed to look in graphic format, I am very confused on how it is supposed to look. Please do not type up the diagram, the text does not translate well. Please make it a graphic.

Then, what would happen if activity E refueling/water service was reduced to 15 min? How would it change time to completion and the critical path?

Please help me find the critical path (I think it is B,

Activity Description Immediate Predecessors Time (Min) A Aircraft stops at the gate :00 B Jet bridge connected A :05 Passengers deplane B :10 Baggage offloaded A :15 Refueling/water servicing T MO D :25 Gallery servicing C :20 Cabin cleaning C H :20 Baggage loaded D :15 Passengers boarded E, F , G :15 Aircraft ready for departure H , I Actual 1 plan Duration start CTIVITY PLAN START PLAN PERIOD DURATION S A: Aircraft stops at 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 gate B: Jet bridge connected C: Passengers deplane 10 D: Baggage Offloaded 15 15 E: Refueling/water ervicing 25 25 F: Galley servicing 40 20 G: Cabin cleaning 40 20 H: Baggage loaded 55 15 1: Passenger boarded 35 15 I: Aircraft ready for departure 70 85 Duration ES EF 15 25 40 000 505 5 5 10 15 10 25 25 25 50 20 50 70 15 55 70 15 70 85 20 70 90

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!