Question: Please help me solve a-c Problem 9-13 (Algorithmic) Suppose that the following estimates of activity times (in weeks) were provided for the network shown below:

Please help me solve a-c

Problem 9-13 (Algorithmic)

Suppose that the following estimates of activity times (in weeks) were provided for the network shown below:

Activity Optimistic Most Probable Pessimistic
A 3 4 5
B 1.5 2 2.5
C 7 8 9
D 4.5 5 7
E 3 6 9
F 1 2 3
G 9 11 13
H 8 9 16

Assume that the critical pass is A-C-H. Based only on the critical path, what is the estimated probability that the project will be completed. If required, round your answers to two decimal places.

  1. Within 21 weeks? fill in the blank 1
  2. Within 22 weeks? fill in the blank 2
  3. Within 25 weeks? fill in the blank 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!