Question: Please help me solve a-c Problem 9-13 (Algorithmic) Suppose that the following estimates of activity times (in weeks) were provided for the network shown below:
Please help me solve a-c
Problem 9-13 (Algorithmic)
Suppose that the following estimates of activity times (in weeks) were provided for the network shown below:
| Activity | Optimistic | Most Probable | Pessimistic |
| A | 3 | 4 | 5 |
| B | 1.5 | 2 | 2.5 |
| C | 7 | 8 | 9 |
| D | 4.5 | 5 | 7 |
| E | 3 | 6 | 9 |
| F | 1 | 2 | 3 |
| G | 9 | 11 | 13 |
| H | 8 | 9 | 16 |
Assume that the critical pass is A-C-H. Based only on the critical path, what is the estimated probability that the project will be completed. If required, round your answers to two decimal places.
- Within 21 weeks? fill in the blank 1
- Within 22 weeks? fill in the blank 2
- Within 25 weeks? fill in the blank 3