Question: Please help me solve this assignment! Thanks! The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS) a m
Please help me solve this assignment! Thanks!
The following represents a project that should be scheduled using CPM:
| ACTIVITY | IMMEDIATE PREDECESSORS | TIMES (DAYS) | ||
|---|---|---|---|---|
| a | m | b | ||
| A | 1 | 4 | 7 | |
| B | 1 | 3 | 5 | |
| C | A | 2 | 5 | 11 |
| D | A | 1 | 8 | 9 |
| E | B | 1 | 2 | 3 |
| F | C,D | 1 | 6 | 11 |
| G | D,E | 1 | 2 | 3 |
| H | F,G | 2 | 3 | 3 |
b. What is the critical path?
- A-C-F-H
- A-D-F-H
- A-D-G-H
- B-E-G-H
c. What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.
d. What is the probability of completing this project within 22 days?
Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and the final answer to 4 decimal places.