Question: Problem 4-10 (Algo) The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS) a m b A 1 3
Problem 4-10 (Algo)
The following represents a project that should be scheduled using CPM:
| ACTIVITY | IMMEDIATE PREDECESSORS | TIMES (DAYS) | |||
|---|---|---|---|---|---|
| a | m | b | |||
| A | 1 | 3 | 8 | ||
| B | 1 | 2 | 9 | ||
| C | A | 2 | 3 | 7 | |
| D | A | 1 | 2 | 12 | |
| E | B | 1 | 2 | 3 | |
| F | C,D | 1 | 3 | 5 | |
| G | D,E | 1 | 7 | 13 | |
| H | F,G | 2 | 5 | 13 | |
b. What is the critical path?
multiple choice
A-C-F-H
B-E-G-H
A-D-F-H
A-D-G-H Correct
c. What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.
| roject completion time | 15.000selected answer incorrect | days |
d. What is the probability of completing this project within 20 days?
Note: Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.
| robability | 0.8873 not correct |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock