Question: Please help me solve this project management monitering problem. Problem 2. (1 point) The Cove at UP is looking to implement a new ERP system.

Please help me solve this project management monitering problem.

Problem 2. (1 point) The Cove at UP is looking to implement a new ERP system. Caitlin Elizabeth developed a project plan and identified the following tasks, precedence relations, normal task durations, labor costs (i.e. run rates), and fixed costs:

Task Predecessors Tusk Duration Labor Rate Fixed Cost
start 0 0 0
A start 15 1600 13000
B A 41 2800 3300
c A 38 2200 0
D A 12 2000 19900
E B, C 32 1600 15200
F B, c, D 23 800 0
G F 41 800 0
H E, G 19 2800 0
end H 0 0 0

Caitlin has studied project management at the University of Portland and G looking for a student intern. You have been asked to demonstrate your understanding of earned value analysis (EVA) as part of the interview process. Given an ACWP of 441873 and BCWP of 521410, calculate the EVA result at the end of week 139 for each of the following metrics. Note that ES = n should be interpreted as starting at the end of week n. Therefore, a task with duration 2, ES = 4, and EF = 6 would be active during periods 5 and 6.

Find:

BCWS (budget cost of work schedule) ______enter answer to zero decimal places.

CI (cost index) _____ enter answer to 2 decimal places

SI (schedule index)____ enter answer to 2 decimal places

EAC optimistic _____enter answer to zero decimal places.

EAC pessimistic _____enter answer to zero decimal places.

CR (critical ratio)____enter answer to 2 decimal places.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!