Question: please help me with question b. i need help finding the slack for the activitys not on the critical path A project for improving a


A project for improving a billing process has the following precedence relationships and activity times: a. Choose the correct network diagram below Question 2 Question 3 Duestion 4 Question 5 b. Eakculate the slacik for tach activity. Which activties are of the entical pati