Question: PLEASE HELP :') Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the second plane took 16,000 hours to produce. Using an 75%
PLEASE HELP :')
Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the second plane took 16,000 hours to produce. Using an 75% learning curve and a $40-per-hour labor charge, he wants to determine the cost of the four additional planes.
a. Time required for the fourth unit = ? hours (round your response to the nearest whole number).
b. Cost of the fourth unit = ?
c. Time required for the fifth unit ? hours (round your response to the nearest whole number).
d. Cost of the fifth unit = ?
e. Time required for the sixth unit ? hours (round your response to the nearest whole number).
f. Cost of the sixth unit = ?