Question: Please help. thank you MS Project can do its scheduling from ________. the project stop date the project start date the project initiate date either

Please help. thank you

  1. MS Project can do its scheduling from ________.
  1. the project stop date
  2. the project start date
  3. the project initiate date
  4. either the project start date or the project stop date

  1. In MS Project resource hourly costs are entered in the ________.
  1. network chart
  2. entry table
  3. task assignment table
  4. resource sheet

  1. MS Project can do its scheduling from ________.
  1. the project stop date
  2. the project start date
  3. the project initiate date
  4. either the project start date or the project stop date

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!