Question: Please help to draw a network diagram using the below data. WP Descrption ID Predecessors DUR Days 1.1.1.1 Research on Target Market A 0 5
Please help to draw a network diagram using the below data.
| WP | Descrption | ID | Predecessors | DUR Days |
| 1.1.1.1 | Research on Target Market | A | 0 | 5 |
| 1.1.1.2 | Compilation of Business Analysis | B | A | 3 |
| 1.1.1.3 | Development of Technical Specification | C | B | 4 |
| 1.1.2.1 | Identify a Developer | D | 0 | 5 |
| 1.1.2.2 | Develop Statement of Work | E | B | 4 |
| 1.1.3.1 | Development and Approval of Business Model | F | C,E | 5 |
| 1.1.4.1 | Develop prototype of platform | G | F | 3 |
| 1.1.4.2 | Test functionality using test users | H | G | 4 |
| 1.1.4.3 | Troubleshooting and security checks | I | H | 3 |
| 1.1.4.4 | Develop user training package | J | G,H | 5 |
| 1.2.1.1 | Development and loading of API | K | I | 10 |
| 1.2.1.2 | Development of admin panel | L | K | 8 |
| 1.2.1.3 | Integration with online payment software | M | L | 5 |
| 1.2.2.1 | User onboarding | N | M | 8 |
| 1.2.3.1 | Platform testing | O | N | 3 |
| 1.3.1.1 | Recruitment of SMMEs | P | O | 4 |
| 1.3.1.2 | Onboarding and training of SMMEs | Q | P | 3 |
| 1.3.2.1 | Develop advertising plan | R | M | 8 |
| 1.4.1.1 | Develop maintenance startegy and manual | S | M | 8 |
| 1.4.1.2 | Establishment of Support desk | T | M | 6 |
| 1.5.1.1 | Project closure, documentation and handover | U | S,T | 4 |