Question: Please help to solve this question(a), Expert. Thank You Given the following table displaying the logical connections of activities and their durations: Immediate Activity Time
Please help to solve this question(a), Expert. Thank You
Given the following table displaying the logical connections of activities and their durations: Immediate Activity Time (Days) Predecessor A 1 B 3 A 4 A D 2 B E 1 B F 2 DE G 3 C,D H 7 F,G NA a. In the space provided below, draw the network diagram for the activities and calculate the EST and LST of the events and mark on the diagram. (18 Marks)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock