Question: please help View Policies Current Attempt in Progress Sheridan Company has a materials price standard of $2.00 per pound 4300 pounds of materials were purchased
please help
View Policies Current Attempt in Progress Sheridan Company has a materials price standard of $2.00 per pound 4300 pounds of materials were purchased at $2.20 a pound. The actual quantity of materials used was 4300 pounds, although the standard quantity allowed for the output was 4000 pounds. Sheridan Company's materials quantity variance is O $600F $660 F $660U $600 U Save for later Attempts: 0 of 1 used Submit