Question: Please help with e, f , g and ah!!! 1. Consider a process consisting of three resources. Assume there exists unlimited demand for the product,

Please help with e, f , g and ah!!!Please help with e, f , g and ah!!! 1. Consider a

1. Consider a process consisting of three resources. Assume there exists unlimited demand for the product, and that all activities are always performed in the following sequence. - Resource 1 has a processing time of 7 minutes per unit. - Resource 2 has a processing time of 4 minutes per unit. - Resource 3 has a processing time of 5 minutes per unit. All three resources are staffed by one worker and each worker gets paid $15 per hour