Question: please highlight the answer and show your work During the most recent month at Somov Corporation, queve time was 0.75 days, inspection time was 1.1

please highlight the answer and show your work
 please highlight the answer and show your work During the most

During the most recent month at Somov Corporation, queve time was 0.75 days, inspection time was 1.1 days, process time was 0.35 days, wait time was 3.25 days, and move time was 0.15 days. Required a Compute the throughput time: b Compute the manufacturing cycle efficiency (MCE) c. Compute the delivery cycle time