Question: Please, I need 100% reliable answer for this question. Type answer needed. Thanks in advance. Calculate the slack times for each activity, and find out

Please, I need 100% reliable answer for this question. Type answer needed. Thanks in advance.
Calculate the slack times for each activity, and find out the critical path. (calculate and mark directly in the figure) Start 9 B 6 A 39 E 10 D 15 7 F 12 10 H 35 23 FinishStep by Step Solution