Question: please include slack times Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that
please include slack times
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) A B D B E AD F G E, F This exercise contains only parts b, c, and d. Time (days) 2 5 1 10 OW b) The critical activities for the leadership training program development project are