Question: Please include the Critical Path; Project Duration; and Variance The project manager of Good Public Relations gathered the data shown in the following table for


Please include the Critical Path; Project Duration; and Variance
The project manager of Good Public Relations gathered the data shown in the following table for a new advertising campaign. Click the icon to view the table. a. How long is the project likely to take? (Make sure to round all intermediate calculations for te to two decimal places.) The project is expected to take weeks. (Enter your response rounded to two decimal places.) Activity A B D E F G H 1 Optimistic 7 6 6 1 8 5 NANN N 10 Time Estimates (weeks) Most Likely Pessimistic Immediate Predecessor(s) 10 13 START 8 18 START 8 10 START 2 3 B 10 13 AC 6 8 D, E 3 6 D, E 5 9 F, G 4 7 G 5 7 2 2 XL
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
