Question: please let me know the answer for these two An activity X of a project has only two immediate predecessors, whose earliest finish times are

please let me know the answer for these two
please let me know the answer for these two An
An activity X of a project has only two immediate predecessors, whose earliest finish times are 50 and 53, respectively. What is the ES of the activity X? Enter a whole number in the box. Your Answer: 53 I Answer . Question 7 (1 point) Saved An activity Y of a project has only two immediate successors, whose latest start times are 24 and 11, respectively. The duration of Y is 5. What is the LS of the activity Y? Enter a whole number in the box. Your Answer: 6