Question: please let me know the answer for these two An activity X of a project has only two immediate predecessors, whose earliest finish times are
please let me know the answer for these two
An activity X of a project has only two immediate predecessors, whose earliest finish times are 50 and 53, respectively. What is the ES of the activity X? Enter a whole number in the box. Your Answer: 53 I Answer . Question 7 (1 point) Saved An activity Y of a project has only two immediate successors, whose latest start times are 24 and 11, respectively. The duration of Y is 5. What is the LS of the activity Y? Enter a whole number in the box. Your Answer: 6
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
