Question: please let me know the answer for this Given the following sequence of activities, find the activities on critical path and length of critical path.

please let me know the answer for this
please let me know the answer for this Given the
Given the following sequence of activities, find the activities on critical path and length of critical path. Activity A B C D E F G -IOTIC Predecessor Time (days) 5 A 2 A 4 5 B 5 5 E,F 2 D 3 GH 5 A-C-E-G-I, 19 days A-D-F-G-I, 23 days O A-C-F-G-I, 21 days O A-C-F-H-I, 22 days