Question: **Please need help with the last question, I submitted this question before and it was incorrect*** Thank you in advance Currently the manufacturer has six
**Please need help with the last question, I submitted this question before and it was incorrect*** Thank you in advance
Currently the manufacturer has six machines that operate on a two-shift (eight hours each) basis. Twenty days per year are available for scheduled maintenance of equipment. Assume there are 250 workdays in a year. Each manufactured good takes 22 minutes to produce.
-
What is the effective capacity of the factory? Round your answer down to the nearest whole number and use this answer in subsequent computations.
units/year
-
Given the five-year forecast, how much extra capacity is needed each year? Round your answers to the nearest whole number.
Year 1 2 3 4 5 Extra capacity needed (units) -
Does the firm need to buy more machines? If so, how many? When? If your answer is zero, enter "0". Round your answers up to the nearest whole number.
Year 1 2 3 4 5 Additional machines needed