Question: Please, please, quickly Use the table below to solve the following questions: DURATION (DAYS) OPTIMISTIC MOST LIKELY PESSIMISTIC 2 4 7 8 14 ACTIVITY A

Please, please, quickly
Use the table below to solve the following questions: DURATION (DAYS) OPTIMISTIC MOST LIKELY PESSIMISTIC 2 4 7 8 14 ACTIVITY A B D E 5 4 2 6 2 10 8 2 21 7 ? What is the expected duration of Activity A in days 2 4 7 13 4.167 4.33 ? What is the expected duration of Activity B in daysStep by Step Solution