Question: Please produce a fresh answer. Dnt copy an answer . A gantry is to be buit on the side of a steep hill as shomn
Please produce a fresh answer. Dnt copy an answer A gantry is to be buit on the side of a steep hill as shomn below.
a After installing foundations for the identical towers A and a plinth has to be
erected for tower B to compensate for the hill siope. On completion of the plinth a
sighting is taken from its top to determine the height of base to be constructed for
tower to ensure final levelling. The foot of each tower is clamped in position by
a series of securing plates fitted to base A and the plinth.
b The activities to be considered with their esfimated duration and manpower
requirements are:
c Produce an "activity on arrow' network for the project identifying the crifical path
and determine the minimum duration of the project in days. Show total flosat and
free float on your network.
d Produce a tabulated, job oriented, analysis of the network
e Produce a bar chart representation of the network and a resource disgram for
the project.
f What will be the effect if the digging of foundation A activity B was extended to
i Days
i days
If the maximum number of men available on any day was six, could the project be
completed in the mirimum time determined in part d sssuming the digging of
foundation A took the two days scheduled.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock