Question: please provide excel formulas 1. The Pohl Pool Company has seven jobs waiting to be processed through its liner department. Each job's estimated processing times

please provide excel formulas 1. The Pohl Poolplease provide excel formulas

1. The Pohl Pool Company has seven jobs waiting to be processed through its liner department. Each job's estimated processing times and due dates are as follows: Job Processing Time (Days) Due Date (Days from Now) A 4 4 8 B 13 37 3 8 C 6 D 3 7 E 11 39 F 9 9 21 G 8 16 a. Using the shortest processing time scheduling rule, in what order would the jobs be completed? Processing can start immediately. b. What is the average completion time (in days) of the sequence calculated in part a? c. What is the average job lateness (in days) of the sequence calculated in part a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!