Question: PLEASE PROVIDE STEPS and formulas used to get the answer!! Thank you!! The Geneva Watch Corporation manufactures watches on a conveyor belt with 6 stations.
The Geneva Watch Corporation manufactures watches on a conveyor belt with 6 stations. One worker stands at each station and performs the following tasks: ime (in seconds) Workers get paid $10 per hour, per employee. You can ignore any idle time of workers resulting from the beginning or the end of the day. Assume a demand rate of 50 watches per hour. What is the takt time (in seconds)? The takt time is seconds