Question: please send the answer as soon as possible 5- Given the project within the table below calculate (12 Points) a. The critical path b. The

please send the answer as soon as possible
5- Given the project within the table below calculate (12 Points) a. The critical path b. The minimum project duration c. The amount of slack for each activity Immediate Predecessors Activity A B Duration (hours) 3 5 8 6 2 1 4 D E F AB B, C D FStep by Step Solution