Question: Please show all work and make it easy for me to understand and work in Excel. Thank you! SYG Manufacturing Corporation contracted with PEG Motors

Please show all work and make it easy for me to understand and work in Excel. Thank you!
SYG Manufacturing Corporation contracted with PEG Motors to provide motor casings.
According to the contract, SYG should design their assembly line to produce 480 units of
casings in 12 hours. SYG gathered tasks, task times, and sequence requirements shown
below. No cellular layout will be used.
What is the theoretical minimum number of workstations required?
Calculate efficiency for theoretical number of stations and also for following the
immediate predecessor chart?
Calculate idle time for each workstation (Hint, Cycle time minus what you assigned for
each workstation).
 Please show all work and make it easy for me to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!