Question: Please show all work and make it easy for me to understand and work in Excel. Thank you! SYG Manufacturing Corporation contracted with PEG Motors
Please show all work and make it easy for me to understand and work in Excel. Thank you!
SYG Manufacturing Corporation contracted with PEG Motors to provide motor casings.
According to the contract, SYG should design their assembly line to produce units of
casings in hours. SYG gathered tasks, task times, and sequence requirements shown
below. No cellular layout will be used.
What is the theoretical minimum number of workstations required?
Calculate efficiency for theoretical number of stations and also for following the
immediate predecessor chart?
Calculate idle time for each workstation Hint Cycle time minus what you assigned for
each workstation
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock