Question: Please show all work step-by-step 3.29 What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by

Please show all work step-by-step
3.29 What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? PX ACTIVITY NORMAL CRASH NORMAL CRASH IMMEDIATE TIME TIME COST COST PREDECESSOR(S) (DAYS) (DAYS) A 6 5 $ 900 $1,000 B 8 6 300 400 C 4 3 500 600 - D 5 3 900 1,200 A E 8 5 1,000 1,600Step by Step Solution