Question: please show calculations and explain how you got each number. thanks! Example Lead time for this component is 2 weeks and order quantity is 200.
please show calculations and explain how you got each number. thanks!
Example Lead time for this component is 2 weeks and order quantity is 200. Complete the table. What action should be taken? Week 1 2 3 4 50 250 100 50 200 Gross Requirements Scheduled Receipts Projected Available 150 Net Requirements Planned Order Receipt Planned Order Release