Question: Please show every working please. 5. A project has the activities and activity times (days) listed below. Construct a network diagram for the project. Determine

Please show every working please. 5. A project

Please show every working please.

5. A project has the activities and activity times (days) listed below. Construct a network diagram for the project. Determine the probability that the project will be completed in 40 days or less. Expected time Standard deviation Activity 1-2 15 2 2-4 17 1 1-3 14 1.5 3-4 16 0.5