Question: please show network diagram IN EXCEL with all boxes for ES, EF, LS, LF, dur, task name, please do not copy answer from online source.
please show network diagram IN EXCEL with all boxes for ES, EF, LS, LF, dur, task name, please do not copy answer from online source. the answers you copy from online ARE INCORRECT WITH DIFFERENT NUMBERS please do the work yourself
8. You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 17 working days. Draw a project network, given the following information. Complete the forward and backward pass, compute activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project? ID Description Predecessor Time (days) A Prepare site None 2 B Pour foundation A 3 c Erect frame B 4 D Roof 4 E Windows C 1 F Doors C 1 G Electrical 3 H Rough-in-frame D, E, F, G 2 I Door opener F G 1 J Paint HI 2 K Cleanup J 1