Question: Please show part B work. Thanks! Immediate Predecessor(s) Activity A B D Activity Time (weeks) 4 9 6 14 10 4 4 E E F

Please show part B work. Thanks!Please show part B work. Thanks! Immediate

Immediate Predecessor(s) Activity A B D Activity Time (weeks) 4 9 6 14 10 4 4 E E F BC B D D E F G G H 7 a. a. Choose the correct network diagram below. . B. 6 S S F 14 14 B B 9 E 10 9 10 c. OD 14. S 10 D b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack (weeks) A 4 B 9 6 D 14 E 10 F 4 G 4 H 7