Question: please show step by step... The B/C ratio for a flood control project along the Swanee River was calculated to be 1.4. If the benefits
please show step by step...
The B/C ratio for a flood control project along the Swanee River was calculated to be 1.4. If the benefits were $550,000 per year and the maintenance costs were $171,000 per year, determine the initial cost of the project at an interest rate of 8% per year and a 50-year life. The initial cost of the project is $D