Question: please show work 11) Activity Predecessors Expected Duration (in minutes) Variance of Duration (in minutes) A ---- 10 1.2 B A 5 1.00 C A
please show work
11)
| Activity | Predecessors | Expected Duration (in minutes) | Variance of Duration (in minutes) |
| A | ---- | 10 | 1.2 |
| B | A | 5 | 1.00 |
| C | A | 15 | 2.4 |
| D | B, C | 11 | 1.5 |
| E | D | 10 | 1.8 |
|
|
|
|
|
a). For the above projects find the expected duration and standard deviation of the project duration. (6points)
b. Based on your calculations from part a what is the probability that the project will be completed in 50 minutes. (4points)
c. How many minutes will the project be completed, if the company projects 90% probability for completion. (5points)