Question: Please show work. 4. From the information gathered by completing question 3 above, assume the next day after this MRP was run, the supplier of
Please show work.

4. From the information gathered by completing question 3 above, assume the next day after this MRP was run, the supplier of component 1 calls to say that the scheduled receipt of 100 items due in week 1 will be delayed 2 weeks due to a supplier equipment breakdown. a. What impact to the MRP plan will this have (if any) b. What actions should be taken (if any)