Question: Please show work. A bread-making factory has the production process shown in the figure below. There are five operations in sequence. The product only needs
Please show work.

A bread-making factory has the production process shown in the figure below. There are five operations in sequence. The product only needs to go through one of the parallel machines in each case where parallel machines exist. Assume 8 hours per day, 7 days per week, what is the weekly capacity of the process? Proof 60 min./batch Bake Pack Mix 50 min/batch 60 min./batch 40 min./batch Proof Cut 60 min./batch 35 min./batch Mix Bake Pack 50 min/batch Proof 60 min./batch 40 min./batch 60 min./batch 00000 112 batches 96 batches 84 batches 56 batches 67 batches
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock