Question: Please show work, can NOT use Excel, thank you!! Using the Johnson's Rule, what is the ideal sequence? Job A B D E Work Center

Please show work, can NOT use Excel, thank you!! Please show work, can NOT use Excel, thank you!!

Using the Johnson's Rule, what is the ideal sequence? Job A B D E Work Center 1 6 minutes 3 minutes 8 minutes 11 minutes 5 minutes Work Center 2 2 minutes 6 minutes 4 minutes 7 minutes 9 minutes Use the bars below to illustrate (by shading and labeling) how many minutes this sequence will take? (3 points) WS#1 WS#2 (Min) 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36