Question: please show work please answer both questions a (10 points) Schedule the following jobs so as to minimize the number of delayed (Tardy) jobs, using
please show work
please answer both questions
a (10 points) Schedule the following jobs so as to minimize the number of delayed (Tardy) jobs, using the procedure given ion the handout. Job Processing Due date time 12 24 15 15 29 b. Schedule the following jobs which must go through Machine 1 and then Machine 2. Your objective is to minimize the flow time (time from the beginning of the first job to the finish of the last job). Find a sequence and a schedule using Johnson's rule. Draw a chart that goes with your sequence. What is the flowtime as per your chart? Job Processing time in Machine 1 Processing time in Machine 2 Sequence: Schedule Step by Step Solution