Question: Please show work!!! Problem 2. (18 points) The desired daily output for an assembly line is 180 units. This assembly line will operate 450 minutes

Please show work!!!
Problem 2. (18 points) The desired daily output for an assembly line is 180 units. This assembly line will operate 450 minutes per day. The following table contains information on this product's task times and precedence relationships: Task Task Time immediate Name (seconds) Predecessor 1 60 70 K 60 L 70 M 30 K N 130 80 DO MN LO 50 a. Draw the precedence diagram. (5 points) b. What is the workstation cycle time required to produce 180 units per day? (1 points) c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary (tiebreaker) rule. (10 points) d. What is the efficiency of your line, assuming it is running at the cycle time from part b? (2 points) 1Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock