Question: Please show work Suppose demand for cabinets is as given in the table below. Currently there are 3000 cabinets on hand. Production is planned by

Please show work Suppose demand for cabinets isPlease show work

Suppose demand for cabinets is as given in the table below. Currently there are 3000 cabinets on hand. Production is planned by using the fixed order period method with 2 periods grouped together. The lead time to receive an order is 1 period. Period 1 2 3 4 5 16 Demand 400 2000 1500 700 600 1800 On-Hand (3000 to start) Net req's Planned order receipts Planned order releases What are the planned order releases in period 2