Question: please show work with formulas. 1. Demand for a power steering gear assembly is given by Week 12345678910 Demand 1210101578635202525 Currently there are 85 parts
1. Demand for a power steering gear assembly is given by Week 12345678910 Demand 1210101578635202525 Currently there are 85 parts on hand and 20 of it must be considered as safety stock. The lot-sizing rule is fixed order period using two periods. Lead time is three periods. Determine the planned order release schedule for the gear
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts