Question: please show work with formulas. 1. Demand for a power steering gear assembly is given by Week 12345678910 Demand 1210101578635202525 Currently there are 85 parts

please show work with formulas. please show work with formulas. 1. Demand for a power steering gear

1. Demand for a power steering gear assembly is given by Week 12345678910 Demand 1210101578635202525 Currently there are 85 parts on hand and 20 of it must be considered as safety stock. The lot-sizing rule is fixed order period using two periods. Lead time is three periods. Determine the planned order release schedule for the gear