Question: Please Solve all the questions: 9. Approved changes are an output of the Perform Integrated Change Control process. All of the following are true regarding

Please Solve all the questions:

9. Approved changes are an output of the Perform Integrated Change Control process. All of the following are true regarding this process except which one?

A. Baseline changes should be documented in the change control system or the configuration management system.

B. Baseline changes are implemented during the Perform Integrated Change Control process.

C. You should document all the actions taken during this process in the project document updates output.

D. Changes should be reflected from the current point in time forward.

10. The Monitor Stakeholder Engagement process concerns which of the following?

A. Documenting important information about stakeholder interests in the stakeholder management plan

B. Monitoring the communication needs of the project stakeholders so they receive what they need when they need it

C. Documenting contact information and basic information in the stakeholder register

D. Monitoring your stakeholder relationships and making certain they continue to stay engaged on the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!