Question: please solve asap 3.2: Construct the Network Diagram for the Project listed below and identify the critical path and most risky activity. (4 Marks) Project

please solve asap 3.2: Construct the Network

please solve asap

3.2: Construct the Network Diagram for the Project listed below and identify the critical path and most risky activity. (4 Marks) Project Management Final Term Assessment BBA Summer 2020 Activity Duration (days) Dependency A 8 B 5 A C 6 B&H D 8 C tea 9 D&F F 3 C&T G 7 H 8 G I 9 H 5 J 5 I K 2 J L 3 J

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock