Question: Please Solve the following in details ! Q) Earned value (EV) is a way to measure and monitor the level of work completed on a
Please Solve the following in details !
Q)
Earned value (EV) is a way to measure and monitor the level of work completed on a project against the plan. Earned value (EV) is a way to measure and monitor the level of work completed on a project against the plan.
You are a project manager of a project to build machines. Your project is scheduled to last for 12 months with the following characteristics:
- You are to build two machines a month for 12 months.
- Each machine is planned to cost $100.
- It is the beginning of month 10.
- You have built 20 machines and your CPI is 0.87.
Answer the following questions:
- What is the actual cost of the project?
- If the variance experienced so far were to stop, what is the projects estimate at completion?
- What is the percentage of the project that is complete?
- Why the project is over-budget and ahead schedule?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock