Question: Please solve the following problems related to Chapter 7 : Project Management: Below is the table which includes the information of a new project of

Please solve the following problems related to Chapter 7: Project Management:
Below is the table which includes the information of a new project of ABC Inc. Table 1.
\table[[Activity,\table[[Immediate],[Predecessor(s)]],\table[[Time],[(Weeks)]]],[A,-,3],[B,-,5],[C,A,6],[D,B,7],[E,B,5],[F,C, D,5],[G,D, E,8],[H,G, F,9]]
Please answer the following questions:
(1) Draw the network corresponding to the information of Table 1.
(2) Determine the critical path and the expected project duration
(3) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. Please complete Table 2 with your answer.
Table 2.
\table[[Activity,\table[[Earliest],[Start]],\table[[Earliest],[Finish]],\table[[Latest],[Start]],\table[[Latest],[Finish]],Slack],[A,,,,,],[B,,,,,],[C,,,,,],[D,,,,,],[E,,,,,],[F,,,,,],[G,,,,,],[H,,,,,]]
Please solve the following problems related to Chapter 7: Project Management:
Below is the table which includes the information of a new project of ABC Inc. Table 1.
\table[[Activity,\table[[Immediate],[Predecessor(s)]],\table[[Time],[(Weeks)]]],[A,-,3],[B,-,5],[C,A,6],[D,B,7],[E,B,5],[F,C, D,5],[G,D, E,8],[H,G, F,9]]
Please answer the following questions:
(1) Draw the network corresponding to the information of Table 1.
(2) Determine the critical path and the expected project duration
(3) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. Please complete Table 2 with your answer.
Table 2.
\table[[Activity,\table[[Earliest],[Start]],\table[[Earliest],[Finish]],\table[[Latest],[Start]],\table[[Latest],[Finish]],Slack],[A,,,,,],[B,,,,,],[C,,,,,],[D,,,,,],[E,,,,,],[F,,,,,],[G,,,,,],[H,,,,,]]
 Please solve the following problems related to Chapter 7: Project Management:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!