Question: Please solve the following problems related to Chapter 7: Project Management: 1. Below is the table which includes the information of a new project of

Please solve the following problems related to Chapter 7: Project Management:

1. Below is the table which includes the information of a new project of ABC Inc.

Table 1.

Activity

Immediate

Predecessor(s)

Time

(Weeks)

A --- 3
B --- 5
C A 6
D B 7
E B 5
F C, D 6
G D, E 8
H G, F 9

Please answer the following questions:

(1) Draw the network corresponding to the information of Table 1.

(2) Determine the critical path and the expected project duration

(3) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. Please complete Table 2.

Table 2.

Activity

Earliest

Start

Earliest

Finish

Latest

Start

Latest Finish

Slack

A
B
C
D
E
F
G
H

Please type answer and the steps of computation

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!